FG terminates road contracts awarded to Mothercat, Dantata, RCC


The federal government has terminated its contracts with Mothercat, RCC and Dantata & Sawoe for non-performance on the dualisation of the Obajana-Benin road project sections two, three and four.
The Minister of Works, David Umahi, made this known in a statement by his Special Adviser on Media Uchenna Orji, on Monday In Abuja.
Mr Umahi said that the contracts were terminated due to a delay, which led to the expiration of the contracts, awarded on 3 December 2012.

”The Federal Ministry of Works has terminated contract numbers 6136, 6137 and 6138 with Mothercat Ltd, Dantata & Sawoe Construction Ltd and RCC Ltd respectively.

”The projects affected by this termination are the dualisation of Obajana – Benin road and section II, (Okene – Auchi) in Kogi/Edo.
”Others are the dualisation of Obajana – Benin road, section III (Auchi – Ehor) and the dualisation of Obajana – Benin road section IV (Ehor – Benin) both in Edo.
”The termination of the said contracts became necessary in view of the inordinate delay of the affected companies in job performance,’’ he said.

Article Page with Financial Support Promotion

Nigerians need credible journalism. Help us report it.
PREMIUM TIMES delivers fact-based journalism for Nigerians, by Nigerians — and our community of supporters, the readers who donate, make our work possible. Help us bring you and millions of others in-depth, meticulously researched news and information.
It’s essential to acknowledge that news production incurs expenses, and we take pride in never placing our stories behind a prohibitive paywall.
Will you support our newsroom with a modest donation to help maintain our commitment to free, accessible news?
YES, I’LL DONATE TODAY
x
Do this later

Mr Umahi said that it was also due to their failure, neglect and or refusal to fulfil their contractual obligations as required by the standard conditions of the contract.
“This has affected the timely completion of the projects, which has resulted in the expiration of the contracts by effluxion of time.
“The projects which were awarded on December 3 2012 were advertently abandoned by the contractors and no genuine commitment or good faith was shown towards executing the projects after accepting the considerations offered by the Federal Government.
“This thereby is exposing the road users to untold hardship due to the deplorable condition of the projects,’’ he said.
Mr Umahi said that the engineers in charge have, therefore, been directed to take the necessary steps and arrange with the affected companies for a joint measurement of the so far.
”The Federal Ministry of Works under my watch will not condone acts of unseriousness and sabotage by contractors whose plan is to become a clog in the wheel of progress of the Renewed Hope administration.
”Going forward, the government will not hesitate in terminating all projects that are funded but are non-performing,’’ he said.
(NAN)
Share this:

Support PREMIUM TIMES’ journalism of integrity and credibility
At Premium Times, we firmly believe in the importance of high-quality journalism. Recognizing that not everyone can afford costly news subscriptions, we are dedicated to delivering meticulously researched, fact-checked news that remains freely accessible to all.
Whether you turn to Premium Times for daily updates, in-depth investigations into pressing national issues, or entertaining trending stories, we value your readership.
It’s essential to acknowledge that news production incurs expenses, and we take pride in never placing our stories behind a prohibitive paywall.
Would you consider supporting us with a modest contribution on a monthly basis to help maintain our commitment to free, accessible news? 
Make Contribution

TEXT AD: Call Willie – +2348098788999

Source:

News Archives | Premium Times Nigeria